Advertisementspot_img
Monday, November 18, 2024

Delivering Stories of Progress

Advertisementspot_img

Piling works for LRT-1 Cavite Extension begin

Latest article

Advertisement - PS02barkero developers premium website

THEPHILBIZNEWS Partner Hotels

Hotel Okura Manila
Hotel 101
The Manor at Camp John Hay
Novotel Manila
Taal Vista Hotel
Advertisement - PS02barkero developers premium website

After 19 years of waiting, piling works for the Light Rail Transit (LRT) Line 1 Cavite Extension have finally started on September 1.

Following completion of ground investigation and foundation design works, the Light Rail Manila Corporation (LRMC) has started piling works from Dr. Santos Station in ParaƱaque, where right-of-way (ROW) has been cleared.

Piling works involve the construction of supporting piers that will serve as the foundation for the elevated railway structures.

Phase 1 covers seven kilometers of the 11-kilometer LRT-1 Cavite Extension, including the Redemptorist Station, MIA Station, Asiaworld Station, Ninoy Aquino Station, and Dr. Santos Station.

Asiaworld Station will be located parallel to and right beside the ParaƱaque Integrated Terminal Exchange (PITX), and will eventually be connected to the Metro Manila Subway, forming the ParaƱaque Common Station. These are stations where ROW is already free and clear.

Requiring a total of 203 piers, construction of the first 67 piers started on Sept. 1 from Dr. Santos Station to Ninoy Aquino Station. Forty piers from Ninoy Aquino Station to Asiaworld Station and 22 piers from Redemptorist Station to the existing LRT-1 Baclaran Station will begin construction in November 2019, while 74 piers from Asiaworld Station to Redemptorist Station will begin construction in March 2020.

To speed up construction, piling works will be done simultaneously in up to five different areas where ROW is made available.

In cooperation with LRMC, Metropolitan Manila Development Authority (MMDA), and ParaƱaque City Mayor Edwin Olivarez, the DOTr and the Light Rail Transit Authority (LRTA) have been working hand-in-hand to deliver the ROW needed to ensure continuous works along the alignment.

Remaining ROW obstructions to be cleared under Package 1 include auxiliary facilities that will be cleared with the assistance of ParaƱaque City (e.g., traffic lights, plant boxes, and drainage lines), as well as utility lines of Meralco, Maynilad, PLDT, Globe, Eastern Telecommunications, SkyCable, Radius Telecoms, and Cablelink.

Works along the Manila-Cavite Toll Expressway will begin soon, following productive coordination with its operator, the Cavitex Infrastructure Corporation, the Philippine Reclamation Authority, the Toll Regulatory Board, and some remaining property owners, such as Puregold and Aseana City.

The partial operability section of the LRT-1 Cavite Extension Project is targeted to start operations in the fourth quarter of 2021, with measures being taken for the rest of the line to Niog, Bacoor being operational in 2022.

The project is expected to increase LRT-1’s ridership from 500,000 to 800,000 per day, and reduce travel time between Baclaran and Bacoor, Cavite from one to two hours to only 25 minutes. (Press Release)

Advertisement - PS04spot_img

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Advertisement - PS05spot_img
Advertisement - PS01spot_img

Must read

Advertisement - PS03spot_img