Mindful of the increasing demand of customers for a stable supply of electricity, Meralco recently commissioned its new Real 115 kV – 34.5 kV Substation located along Real Road in Calamba City, Laguna. This also aims to relieve the neighboring Calamba Substation and boost available capacity that will benefit customers in the city and those in portions of the cities of Tanauan and Sto. Tomas in Batangas.
The project involved the energization of two (2) 34.5 kV distribution feeders serving enterprise customers, housing complexes and subdivisions, and key establishments such as the Calamba City Hall, and Sto. Tomas Doctors Hospital and Medical Center. Meralco is continuously working to improve its distribution system to deliver safe, sufficient, and reliable power service to its customers as part of its commitment to support the government’s thrust to improve infrastructure and achieve energy security in the country.