Advertisementspot_img
Wednesday, November 6, 2024

Delivering Stories of Progress

Advertisementspot_img

Gov’t releases IRR of grants for private projects under Bayanihan 2 Law

Latest article

Advertisement - PS02barkero developers premium website

THEPHILBIZNEWS Partner Hotels

Hotel Okura Manila
Hotel 101
The Manor at Camp John Hay
Novotel Manila
Taal Vista Hotel
Advertisement - PS02barkero developers premium website

In photo: The committee who signed the IRR on the grant of regulatory relief to private projects under Bayanihan 2 Law. From left, Finance Secretary Carlos Dominguez the committee chairman, Trade Secretary Ramon Lopez, and Environment and Natural Resources Secretary Roy Cimatu.

Photo collage by THEPHILBIZNEWS

By Alithea De Jesus

A committee chaired by the Secretary of the Department of Finance (DOF) has been tasked to identify the private sector projects that will qualify for the grant of regulatory relief under certain conditions as provided for in the Bayanihan To Recover As One Act (Bayanihan 2). 

With the Secretaries of the Department of Environment and Natural Resources (DENR) and the Department of Trade and Industry (DTI) as members, the DOF-led committee was created in compliance with Implementing Rules and Regulations (IRR) of Section 4 (nnn) of Republic Act (RA) No. 11494 or the Bayanihan 2 Law. 

The committee has also been tasked to identify the specific permits, licenses, certificates, clearances, consents, authorizations, or resolutions that shall be waived in accordance with the IRR of this Bayanihan 2 provision. 

Finance Secretary Carlos Dominguez, Trade Secretary Ramon Lopez, and Environment and Natural Resources Secretary Roy Cimatu signed the IRR. 

“The Committee will work towards achieving the goal of the Bayanihan 2 to spur investments by speeding up the approval and implementation of private investments, stimulate economic activity and create jobs, so that our economy can recover from the effects of the COVID-19 pandemic,” Dominguez said.

He added, though, that while the panel has the power to grant regulatory relief and promote investments, “it will not be granting blanket relief as the committee will still carefully consider the over-all contribution of the projects and their impact on the general health and welfare of the public.” 

Lopez said the regulatory relief measures provided under the Bayanihan 2 will “fast-track high impact investments and help our country to build back better and lead to our post-pandemic recovery. It will also allow private projects to provide more employment opportunities for our fellow Filipinos that is critical at this time of the pandemic.”

“While permits, licenses, and other similar authorizations will be waived for private projects that meet the directives of the Act, we will ensure that their proponents comply with all the other laws pertinent to the implementation of these projects,” Cimatu said.

Under Bayanihan 2, private projects determined to be “nationally significant”, ”with high economic returns” or “with high employment potential” may have certain permits,  licenses  or other requirements waived,  to avoid delays in their implementation,  and  immediately stimulate economic activity and create jobs during the state of national emergency declared by the President as a result of the COVID-19 pandemic. 

These regulatory relief measures exclude those relating to taxes, duties, border control and environmental laws and regulations, as stated in Bayanihan 2 and in Section 6 of the IRR. 

Section 4 (nnn) of Bayanihan 2 states that the authority of the committee “shall be valid during the state of national emergency as declared by the President and the economic rehabilitation period or until the last day of June 2022, whichever is later.” 

Under its IRR, the DOF shall serve as the committee secretariat, where the private sector proponent of the project is required to submit the application for regulatory relief.

In identifying which covered projects shall be granted regulatory relief and the specific requirement or requirements that shall be waived, the committee is mandated under the IRR to evaluate them on a per-requirement basis; and determine the economic and social impact of the project (economic returns, job generation potential, effect on the delivery of critical services) on both the national and local economies.  

The committee shall also consider the impact of the lack of the requirement to be waived on the operations and quality of the output of the covered project, and the health and safety of the personnel working on the project, among other factors as stated under Section 5d of the IRR. 

Taking into account the new normal, the IRR states that covered projects under the following sectors may also be considered by the Committee as projects of national significance:

(a) housing and resettlement in support of the Balik Probinsya, Bagong Pag-asa Program (BP2P); 

(b) water supply and sanitation to accelerate achievement of full coverage; 

(c) watershed rehabilitation and protection; 

(d) power generation, transmission and electrification to support the digital economy; and 

(e) provision of other critical services that contribute to providing security and promoting peace.

Moreover, in determining the national significance of a project, the committee shall consider “the significant sectors that would accelerate the recovery and bolster the resilience of the Philippine economy” and may also take into account “the project’s direct and indirect contribution to economic growth and development, implementation readiness, and such other facets that would stimulate the local economy.”    

“As such, the total project cost of the Covered project is not necessarily the sole basis in determining national significance,” the IRR states. 

Section 10 of the IRR prohibits any court, except the Supreme Court (SC), from issuing any temporary restraining order (TRO), preliminary injunction or preliminary mandatory injunction against the Committee and the operation of the Covered project granted regulatory relief.

A technical working group (TWG) composed of representatives from the DOF, DTI, DENR and other government agencies identified by the Committee may be created to serve as its technical arm in evaluating applications, the IRR states. 

The TWG is responsible for conducting the necessary inter-agency coordination and consultation in evaluating the applications for regulatory relief; and in submitting  a comprehensive report to the Committee with its recommendations supported by factual, technical and legal reasons. 

The procedures and requirements in applying for regulatory relief and the limitations and coverage of such relief measures are outlined in the IRR. 

It also states that “(t)he Committee shall not be held liable if there will be a subsequent finding by the appropriate agency that the application should be disapproved.”

Under the IRR, any approval of regulatory relief by the Committee may be revoked at any time in case the project “is determined to have violated any condition given in the grant of such relief.” 

The IRR took effect following its publication in a newspaper general circulation on January 7, 2021.

The Office of the National Administrative Registrar of the University of the Philippines (UP) Law Center, the official repository of all IRRs issued by the different agencies of the government, were provided three (3) certified copies of the new IRR. 

Advertisement - PS04spot_img

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Advertisement - PS05spot_img
Advertisement - PS01spot_img

Must read

Advertisement - PS03spot_img